Hydro project on Yamuna 'bitter lesson' for those calling it cheap green energy source

By Bhim Singh Rawat* 

The 120 Mw Vyasi HEP built by Uttarakhand Jal Vidyut Nigam Ltd (UJVN Ltd.) in Vikas Nagar tehsil of Dehradun is on its way to become the textbook example of how thoughtlessly pushed hydro power projects are proving a nightmare for local people, a costly affair for the state and the nation and a disaster for free-flowing living river.
The project offers some bitter lessons for the policy-makers, experts and society who have been assuming that hydro power is a cheap, green source of energy and the Run of River (RoR) projects don’t dam and cause much harm to the environment, people or rivers.

Past violations unpunished

Like the case with most of hydro projects in the Himalayan region; the Vyasi HEP too has missed several deadlines and suffered cost escalation from Rs. 936.23 crores in February 2010 to Rs. 1777.30 crores upto September 2021.
While in the making for over a decade, the contractor companies brazenly violated several environmental norms including those meant for safe disposal of tunnel debris and construction muck. The project also caused large scale illegal mining in the Yamuna to secure construction materials from the same Yamuna river.
However, in absence of credible monitoring or compliance mechanism, UJVNL have never been held accountable for the irregularities and destruction. There is no information regarding compensatory afforestation against diversion of about 100 hectares of forest land for the project.

Impact on river, people during filling up

The project was prematurely inaugurated in December 2021 but actually came into operation in April 2022 without addressing the Rehabilitation & Resettlement (R&R) rights of agitating Lohari villagers. About 72 homes of the tribal village and several acres of fertile lands have been drowned into the Vyasi dam. Continuing their struggle, many of the displaced families have still been taking temporary shelter in a nearby school.
Meanwhile, with the project commissioned, the unrealistic claims made by UJVNL have also been exposed while the adverse impacts on river ecology are still unfolding. It all began with mass annihilation of fresh water species including the endangered Mahseer fish in huge numbers both in the impounded as well as flowless Yamuna river downstream the dam.T
he farmers from scores of villages dependent on Katapathar canal suffered lack of irrigation water for about three months as the filling up the giant reservoir decreased water flow into the canal from about average 6 cumecs to 1.5 cumecs only. The situation turned so bad that there were fierce protests forcing UJVNL to attend to farmers’ demand.

Yamuna: Once free flowing, now dammed river

Today, the 86-meter-high gravity dam with a 13.69 million cubic metre gross storage capacity has confined a free flowing and living Yamuna into a about 4 km long reservoir extending along 73 hectares of river banks. With this precious fresh water eco-system including riverine vegetation has been lost into the stagnant water body. Notably, this stretch of Yamuna has been among few unthreatened habitats of Mahseer fish.
There has been no independent assessment on ecological impact of the project before the construction and no plan to address the same even after its being operational. UJVNL has built a fish tank downstream the dam with a plan to rear the fish there and release them in the river. The tank is serving no purpose currently.

Dam filled but the project lacks water to run

Ever since its commissioning, the project has been struggling to generate the power according to its designed capacity of 120 MW as there is lack of required flow in the river. Except for few weeks in monsoon months, the UJVNL has been able to run the project only to a quarter or at most half its installed capacity.
Even during monsoon season, power generation has been compromised by the amount of silt and flood level in the river. The water flow in the river during winter are usually lower than monsoon and summer.
In the peak summer season of June 2023, the Vyasi HEP is kept operational for just about 10 hours from 01:00 pm to 11:00 pm generating about 45 Mw for about 7 initial hours and 120 MW for about last 3 hours. The generated power is being sold to the Power Transmission Corporation of Uttarakhand Ltd. (PTCUL) at Rs 7 per unit. The PTCUL further transmits and distributes the power to the Uttarakhand Power Corporation Limited (UPCL) or national grid according to the demand placed which varies on daily basis.
Clearly, the Vyasi HEP is somehow managing to operate at less than half of its installed capacity even in summer. The main reason behind the gross under performance is outdated, biased assessment reports based on which the project was pushed, these reports grossly underestimated significant decline in overall flows in Yamuna and its tributaries over the years on account of man-made reasons as well as climate change.
Muck from Vyasi HEP tunnel dumped close to the river bank
Given the ongoing and planned tapping of feeding streams and Yamuna itself for growing potable water and irrigation requirements in the catchment, there is likely to be a further decline in flowing water in the river in future. A case in point is Rs. 144 crore Mussoorie water project which is in final stages and would pump out 12 MLD of Yamuna water some 20 km uphill upstream from the Vyasi HEP site.

A farce called e-flows

In the name of environmental flows (e-flows), the UJVNL has been releasing just 5 cumecs of water downstream the river through an inbuilt pipe in dam structure. More than half this e-flow is comprised of the seepages collected inside the dam. The dam gates are opened only for repairing, desiltation purposes or when dam is filled to its capacity.
Project was prematurely inaugurated in Dec 2021 and came into operation in April 2022 without addressing the R&R rights
As a result, about 6 km long stretch of the river between dam at Juddo and power station at Hathyari is deprived of essential flows where the aquatic lives struggle to survive in the almost flowless river. This is despite two perennial streams joining the Yamuna between the dam and power station of the project.
As per local people, the situation was even worse in 2022-23 winter months than the current summer season. They said that the mighty Yamuna was reduced to a trickle between project dam and Dakpathar barrage causing frequent deaths of fish and other aquatic lives. The UJVNL and Central Water Commission (CWC) are required to remedy the situation on urgent basis.

Hungry waters turning river into danger zone

Another serious problem created by the Vyasi HEP is that the project has converted the otherwise safe river banks into a danger zone for local people, tourists and domestic animals. The silt free water known as hungry waters discharged from the power station of the project has been causing sudden fluctuations in the river which is detrimental to the proliferation of the aquatic eco-system.
The project has altered the natural flowing pattern of the Yamuna and greatly increased the eroding capacity of the river which is evident from the fact that the river is dangerously eating into its left bank along the Bausan village, downstream the project.
The average inflows in the river during third week of Jun 2023 have been around 30 cumecs. While the dam has strangulated the river of flows, the power station, when it operates, has been dumping about twice or three time more silt free water than the river would have carried in natural state.
The UJVNL has placed several warning boards, installed sirens at three places and deployed a mobile van plying along the 20 km of the project affected area alerting people to stay away from the river. But these measures appear inadequate to prevent any untoward incident.
The local people have found the deafening noise of the sirens annoying, sometimes blaring out in the dead of night which has been toned down following complaints. The farmers and fishermen have been trying to get accustomed with artificially controlled flows and floods in the river. They have to stay watchful for their wards and cattle whenever the sirens blare out

Vyasi HEP disaster preparedness lagging behind

This is so far the tallest and biggest dam on main stem of Yamuna in a geologically and climatically vulnerable region. The project area has been riddled with new and old recurring landslides. Only in August 2021, there have been cloud bursts induced flash floods both at the power station and dam area impacting the project. Despite this. UJVNL has not installed the Early Warning System (EWS).
Hiding Behind Lakhwar Dam
As the adverse impacts and failures of Vyasi HEP have come in open, the UJVNL and contractors’ lobby have started promoting Lakhwar dam as a panacea for all the shortcomings of the Vyasi HEP. Recently the L&T company is learnt to have secured Rs. 3200 crore tenders for civil construction work of the Lakhwar dam project and has started building shelters for workforce there. The work on the dam is reportedly to begin after the south west monsoon 2023.
The proposed massive 204-m high Lakhwar dam, if built, will further turn more than 40 km stretch of free-flowing Yamuna into a watery grave apart from submerging over 50 villages. Sadly, in the global era of large dam removal and in the face of growing dam induced disasters in Himalayan region, the Indian government is still investing in such multi-billion giant dam project on the basis of four-decade old questionable feasibility and EIA reports to cover up the follies of Vysai HEP instead of learning lessons from it.
---
*Source: South Asia Network on Dams, Rivers and People

Comments

TRENDING

King Corona and his descendents: How long will the Dynasty last?

By Dr Amitav Banerjee, MD*  “Corona ” is in the media once again, precipitating a dĆ©jĆ -vu feeling and some amount of panic among the people. Among viruses and microorganisms King Corona and its descendents enjoy Royalty Status. "What's in a name? That which we call a rose by any other name would smell as sweet." This classic quote from Shakespeare's Romeo and Juliet is well known. But does it hold well in current times? The events during the past five years challenge the Bard's view.

India’s 2021 excess deaths: was it the virus — or the containment frenzy?

By Bhaskaran Raman* Tyagu (name changed), a vegetable vendor recalls of his brother’s death in 2021. The victim had a normal fever, but was forcibly taken away to the hospital saying that it was Covid. He had been coerced into taking the Covid-19 “vaccines” by that time. After 10 days in hospital, he died. There was no proper information during his hospital stay, and no one was allowed to visit, saying that visitors could also get Covid.

Old bias, new excuses: How western media misrepresents India’s anti-terror strikes

By Gajanan Khergamker  The recent Indian military strikes on Pakistan, dubbed Operation Sindoor, have sparked a storm of international media coverage. Several prominent outlets have portrayed India as the aggressor in the escalating conflict, raising concerns over biased reporting. This commentary critiques coverage by foreign media outlets such as The New York Times , Reuters, BBC, and CNN, which have often been accused of framing India’s actions as escalatory while downplaying or omitting critical context regarding Pakistan’s role in fostering terrorism. By examining historical patterns and current geopolitical dynamics, this analysis highlights the recurring selective framing, omission of evidence, and a tendency to favor narratives aligned with Western geopolitical interests over factual nuance.

जैविक जीवित संसाधनों व प्रकृति पर निर्भर मजदूरों की व्यापक आर्ऄिक सुरक्षा कैसे हो?

- राज कुमार सिन्हा*  भारत में  60 करोą„œ से अधिक लोग भूमि, जल, जंगल और समुद्र जैसे प्राकृतिक स्रोतों पर निर्भर हैं । देश में 14.6 करोą„œ छोटे और सीमांत किसान, 14.4 करोą„œ खेतिहर मजदूर ( ą¤¬ą„œी संख्या में दलित हैं), 27.5 करोą„œ वन निवासी, 2.8 करोą„œ मछुआरे, 1.3 करोą„œ पशुपालक और 1.7 करोऔ़ कारीगर हैं जो सीधे तौर पर  प्रकृति के साऄ और प्रकृति के भरोसे काम कर रहे हैं । लगभग 6 करोą„œ मौसमी मजदूर हैं जो काम के सिलसिले में लगातार अपने गांव से बाहर जाते हैं और लौटते हैं। प्रकृति निर्भर समुदायों की आर्ऄिक गतिविधियां जो ą¤¬ą„œे पैमाने पर जीवन निर्वाह और छोटी आय के लिą¤ है। वर्तमान आर्ऄिक नीतियों के कारण, जो कॉर्पोरेट्स और ą¤¬ą„œे व्यवसायों का समर्ऄन करती है, प्रकृति निर्भर समुदाय के लिą¤ अव्यवहारिक होती जा रही है। 

राजस्ऄान, मध्यप्रदेश, पश्चिम बंगाल, ą¤ारखंऔ और केरल फिसऔ्औी: जल जीवन मिशन के लक्ष्य को पाने समन्वित प्रयास जरूरी

- राज कुमार सिन्हा*  जल संसाधन से जुऔ़ी स्ऄायी समिति ने वर्तमान लोकसभा सत्र में पेश रिपोर्ट में बताया है कि "नल से जल" मिशन में राजस्ऄान, मध्यप्रदेश, पश्चिम बंगाल, ą¤ारखंऔ और केरल फिसऔ्औी साबित हुą¤ हैं। ą¤œą¤¬ą¤•ि देश के 11 राज्यों में शत-प्रतिशत ग्रामीणों को नल से जल आपूर्ति शुरू कर दी ą¤—ą¤ˆ है। रिपोर्ट में समिति ने केंद्र सरकार को सिफारिश की है कि मिशन पुरा करने में राज्य सरकारों की समस्याओं पर गौर किया जाą¤। 

Crying air, water, and earth: A call to conserve our dying natural resources

By Dr. Gurinder Kaur*  Air, water, and earth—these natural resources are essential for the survival of all living beings, including humans, animals, and plants. Life in any form is impossible without them. These are precious gifts of nature to humankind. However, in the pursuit of economic growth, modern humans have severely polluted these valuable resources in an attempt to satisfy their greed.

The WHO Pandemic Agreement: Why India should reconsider its stance

By Dr Amitav Banerjee, MD*  For more than the past three years, the WHO has been trying its best to push the Pandemic Treaty and amendments to the International Health Regulations in unholy haste, instead of conducting a proper appraisal of the impact of the measures taken during the Covid-19 pandemic—a routine exercise after any pandemic to guide future strategies.  This raises questions about whether the WHO, under China’s influence, is trying to conceal its acts of omission and commission during the pandemic, including obstructing investigations into the origins of SARS-CoV-2. The WHO recently faced a setback when the USA decided to cut all ties with the organization. 

21-day security operation targets Maoist presence, prompts questions on civil impact

By Harsh Thakor*  Union Home Minister Amit Shah has described a recent counter-insurgency operation along the Chhattisgarh-Telangana border as a significant achievement for Indian security forces in their efforts against Maoist groups. The three-week-long operation in the Karreguttalu Hills reportedly resulted in the deaths of 31 individuals identified as members of Maoist formations.

Civil society group voices concern over government response to Pahalgam attack

By A Representative  Citizens for Democracy (CFD), a civil society group, has expressed serious concern over the government's response to the recent terror attack in Pahalgam, Jammu and Kashmir. While unequivocally condemning the violence, CFD raised alarm about what it sees as an excessive and politically motivated reaction by the authorities. CFD acknowledged the widespread condemnation of the attack from all sections of society, including strong protests led by local Kashmiri Muslims. However, it criticized the government for failing to provide a transparent account of the security lapses that allowed the attack to occur. It also noted the absence of a clear plan for accountability or a high-level inquiry into the incident. The group questioned the initiation of Operation Sindoor, describing it as a move driven more by domestic political considerations than strategic necessity. CFD warned that such military actions risk long-term instability and divert attention from peaceful an...